Last week, Bill de Blasio released a plan for New York’s future called OneNYC, whose section on subway expansion called for a subway under Utica Avenue in Brooklyn (PDF-pp. 45-46). The call was just a sentence, without mention of routing or cost or ridership projections, and no plan for funding. However, it remains a positive development; last year, I put the line at the top of a list of underrated subways in North America. Presumably the route would be a branch off the Eastern Parkway Line, carrying the 4, while the 3 continues to go to the current New Lots terminus.
The cost is up in the air, which means that people forming opinions about the idea don’t have the most important and variable number with which to make decisions. In this post, I am going to work out the range of cost figures that would make this a worthwhile project. This has two components: coming up with a quick-and-dirty ridership estimate, and arguing for a maximum acceptable cost per rider.
Before doing anything else, let us look at how much such a subway extension should cost, independently of ridership. Between Eastern Parkway and Kings Plaza, Utica is 6.8 km. The non-English-speaking first-world range is about $300 million to $3 billion, but around $1.4 billion, or $200 million/km, is average. Utica is a wide, relatively straight street, without difficult development alongside it. In fact, I’ve been convinced in comments that the line could be elevated nearly the entire way, south of Empire Boulevard, which would reduce costs even further. Normal cost should then be around $100 million per km (or $700 million), and even in New York, the JFK AirTrain came in at a $200 million/km. I doubt that an elevated solution could politically happen, but one should be investigated; nonetheless, a $1.4 billion subway would be of great benefit.
Now, let us look at ridership. Recall that Utica’s bus route, the B46, was New York’s third busiest in 2014, with 46,000 weekday riders. But two routes, Nostrand’s B44 and Flatbush’s B41, run parallel and provide similar service, and have 67,000 riders between them. Those numbers are all trending down, as residents gradually abandon slow bus service. A subway can realistically halt this decline and generate much more ridership, via higher speed: B46 limited buses average 13 km/h south of Eastern Parkway, but a new subway line could average around 35 km/h. Second Avenue Subway’s ridership projection is 500,000 per weekday, even though all north-south bus lines on Manhattan’s East Side combined, even ones on Fifth and Madison Avenues, total 156,000 daily riders.
Vancouver is considering replacing its busiest bus, the 99-B, with a subway. The 99-B itself has 54,000 weekday riders, the local buses on Broadway (the 9 and 14) have 43,000, and the 4th Avenue relief buses (the 4, 44, and 84) add another 27,000. Those are much faster buses than in New York: the 99-B averages 20 km/h, while the 44 and 84, running on less crowded 4th Avenue, average nearly 30 km/h west of Burrard. SkyTrain is faster than the New York subway since it makes fewer stops, so the overall effect would be similar, a doubling of travel speed, to about 40 km/h. The ridership projection is 250,000 per weekday in 2021, at opening, before rezoning (see PDF-p. 75 here). This represents a doubling of ridership over current bus ridership, even when the buses provide service SkyTrain won’t, including a one-seat ride from the Westside to Downtown and service along 4th Avenue.
In New York, as in Vancouver, the subway would provide service twice as fast as current buses. The distance between Nostrand and Utica Avenues is much greater than that between 4th Avenue and Broadway in Vancouver, so the analogy isn’t perfect (this is why I also support continuing Nostrand down to Sheepshead Bay). Conversely, the speed advantage of subways over buses is greater than in Vancouver. Moreover, Nostrand already has a subway, so actual demand in southeastern Brooklyn is more than what the B41, B44, and B46 represent. A doubling of ridership over bus ridership, to about 220,000, is reasonable.
For a quick sanity check, let us look at Nostrand Avenue Line ridership again. South of Franklin Avenue, the stations have a combined weekday ridership of 64,000 per weekday, as of 2014. But this is really closer to 128,000 daily riders, counting both boardings and alightings; presumably, few people ride internally to the Nostrand corridor. The Nostrand Avenue Line is 4.3 km long; scaled to length, we get 200,000 weekday riders on Utica.
Put together, a normal-cost Utica Line, with 200,000 weekday riders, would cost $7,000 per rider. This is quite low even by non-US standards, and is very low by US standards (Second Avenue Subway Phase 1 is about $23,000 according to projections, and is lower than most US rail lines).
As far as I’ve seen, from glancing at lines in large cities such as London, Paris, and Tokyo, the normal cost range for subways is $10,000-20,000 per rider. Paris is quite cheap, since its ridership per kilometer is so high while its cost per kilometer is not very high, keeping Metro extensions in the four figures (but Grand Paris Express, built in more suburban geography, is projected at $34 billion for 2 million daily passengers). Elsewhere in Europe, lines north of $20,000 are not outliers. If we set $25,000/rider as a reasonable limit – a limit which would eliminate all US rail lines other than Second Avenue Subway Phase 1, Houston’s light rail extensions, and Los Angeles’s Regional Connector – then Utica is worth $5 billion. A more generous limit, perhaps $40,000 per rider to allow for Second Avenue Subway Phase 2, would boost Utica to $8 billion, more than $1 billion per km. Even in the US, subways are rarely that expensive: the Bay Area’s lines are only about $500 million per km.
The importance of the above calculation is that it is quite possible that Utica will turn out to have a lower projected cost per rider than the next phase of Second Avenue Subway, a project for which there is nearly universal consensus in New York. The original cost projection for Second Avenue Subway’s second phase was $3.3 billion, but will have run over since (the projection for the first phase was $3.7 billion, but actual cost is nearly $5 billion); the ridership projection is 100,000 for each phase beyond the first, which is projected at 200,000. In such a situation, the line would be a great success for New York, purely on the strength of existing demand. I put Utica at the top of my list of underrated transit projects for a reason: the line’s worth is several times its cost assuming world-average per-km cost, and remains higher than the cost even at elevated American prices. The de Blasio administration is doing well to propose such a line, and it is nearly certain that costs will be such that good transit activists should support it.